The Project Manager’s Roles in Reducing the Occurrence of Variation Order (VO) on Construction Project

Open access

Nur’Ain Ismail, Mohamad Hilmi Abd Halim, Wan Norizan Wan Ismail, Siti Sarah Mat Isa, Norhafizah Yusop

Pages 48-53 Received: 03 Feb, 2023 Revised: 05 Mar, 2023 Published Online: 07 Apr, 2023

http://dx.doi.org/10.46886/IJARBSS/v13-i4/9251
Among the roles of the project manager in a project execution is to control the occurrence of variation orders. This research aims to determine the project manager’s roles in reducing the occurrence of variation orders in a construction project. The research data were gathered via responses from project managers of construction companies via a questionnaire survey. The 122 responses obtained were then analysed using descriptive analysis. Out of the eight (8) project manager roles tested in the questionnaire survey, it was found that all of them are significant in helping to reduce the occurrence of variation orders in a construction project. The most significant role of the project manager in reducing the occurrence of variation orders in a construction project was effective communication between stakeholders. Good transparency in communication initiated by the project manager could avoid conflicts related to the contract documents. This research provides additional information and knowledge for researchers in further research as well as practitioners to constantly reduce the variation order on construction projects.
Alaryan, A., Elshahat, A., & Dawood, M. (2014), Causes and Effects of Change Orders on Construction Projects in Kuwait. Journal of Engineering Research and Applications, 4(2): 1-8.
Arain, F. M., and Pheng, L. S. (2005b). 'How Design Consultants Perceive Causes of Variation Orders for Institutional Buildings in Singapore', Architectural Engineering and Design Management, vol. 1, no. 3, pp 181-196
Dickson, O. D., Gerryshom, D. M., & Wanyona, D. G. (2014). Factors Contributing to Variation Orders: A survey of Civil Construction Project in Kenya. Journal of Social Sciences and Entrepreneurship, 1(13): 425-437.
Hanna, A. S., Calmic, R., Peterson, P. A., Nordheim, E. V. (2002), ‘Quantitative Definition of Projects Impacted by Change Orders’, Journal of Construction Engineering and Management, vol. 128, no. 1, pp 57-64.
Khurshid, M. B., & Nauman, S. (2016). Impact of Variation Orders on Time & Cost in Mega Hydropower Projects of Pakistan. Journal of Construction in Developing Countries. 5(1): 54-68.
Malyavin, I. (2014). Report on the Project Management in Construction: Construction Contracts and Contract Variations. Auckland University of Technology School of Engineering.
Mohammad, N., Ani, A., Rakmat, R., Yusof, M. (2010). Investigation on the causes of variation orders in the construction of building project–a study in the state of Selangor, Malaysia. Journal of Building Performance, 1.
Ngwepe, L., Aigbavboa, C., & Thwala, W. (2015) The Critical Determinants of Variation Orders on SA Public Sector Construction Projects. Journal of Engineering & Built Environment, 7 (2): 68-77.
Ruben, N. (2008), "An analysis of the impact of variation
Ruben, N. (2008), "An analysis of the impact of variation orders on project performance", Cape Peninsula University of Technology, Theses & Dissertations, Paper 33
Technology, Theses & Dissertations, Paper 33
Thomas, R., Horman, J., De Souza, L., & Zavrski, I. (2002), ‘Reducing Variability to Improve Performance as a Lean Construction Principle’, Journal of Construction Engineering and Management, vol. 128, no. 2, pp 144-154.
Wambeke, B. W., Hsiang, S. M., Liu, M. (2011). Causes of variation in construction project task starting times and duration. Journal of Construction Engineering and Management, 137, 663-677.
Zewdu, T. (2015). Report on the Causes and Effects of Variation Orders in Road Construction Projects: The case of national works contract administered by Addis Ababa city roads authority. Addis Ababa University School of Graduate Studies.