Identification Type of Risk with Evidence to Kelantan’s Flyover Projects

Open access

Fairiz Miza Yop Zain, Arifatun Aqilah Mohamed, Mohamad Tajudin Saidin, Mohd Firdaus Zainuddin

Pages 1485-1490 Received: 14 Jun, 2022 Revised: 17 Jul, 2022 Published Online: 12 Aug, 2022

http://dx.doi.org/10.46886/IJARBSS/v12-i8/12387
Risk management is a process to determine the project risks, analyse them, and decide on how to avert the risks on any project. However, steps in the risk management process should be included to deal with risks existed. Therefore, the objective of this paper is to determine common risks within the construction process of the flyover construction in Kelantan. For this research, the method used was the quantitative method by using a questionnaire survey. The respondents of this research were contractors G7 located in Kelantan. A total of 84 questionnaires were distributed, with 54 returned them. The analysis on the data collected was executed through the use of Statistical Packages for Social Science (SPSS) program. The collection of information was analysed thoroughly to produce a definite conclusion from the research that may help with the issue. The findings showed that ten items were identified. The result revealed that an escalation of construction material prices, unexpected subsurface conditions that cause difficulty to execute subsurface-related works and climates of weather problems that affect the construction progress and damages to a person’s property or materials were crucial type of risks in construction process of the flyover construction in Kelantan. Further study suggests the study on risk management in more depth, widely and focusing on a project in Malaysia.
Abdul-Rahman, H., Wang, C., & Mohamad, F. (2015). Implementation of Risk Management in Malaysian Construction Industry: Case Studies. Journal of Construction Engineering. 2015. 1-6. 10.1155/2015/192742.
Adeleke, A., Bahaudin, A., & Kamaruddeen, A. (2016). Moderating Effect of Regulations on Organizational Factors and Construction Risk Management: A Proposed Framework. International Journal of Economics and Financial Issues, 6(7S), 92-97.
Adeleke, A. Q., Nawi, M., Nasrun, M., & Abd-Karim, S. B. (2020). Where Are We? The Level of Risk Management in Malaysian Construction Industries., 7(1), 527-532.Choudhry, R. M., & Aslam, A. M. (2109). Risk Analysis of Bridge Construction Projects in. Abc.
Fincham, J. E. (2008). VIEWPOINTS Response Rates and Responsiveness for Surveys, Standards, and the Journal. http://jcmc.indiana.edu/vol6/issue1/yun.html
Omer, M. S. (2019). Level Of Risk Management Practice In Malaysia Construction Industry From A Knowledge-Based Perspective. Journal of Architecture, Planning and Construction Management, 9(1).
Khodeir, & Mohamed, L. (2017). Efficient Risk Management: Cause and Effect Analysis of Key Risks of Complex Construction Projects in Egypt. JES. Journal of Engineering Sciences, 45(6), 773–790. https://doi.org/10.21608/jesaun.2017.116886
Mokua, N. W. (2014). Evaluation of Success Indicators of Building Construction Projects in Kenya. November.
Patil, G. L. (2019). Risk analysis in flyover construction. 4(8), 27–32.
Petrovic, D. (2017). Risk Management in Construction Projects - A Knowledge Management Perspective from Swedish Contractors. Real Estate and Construction Management, 63.
Porter, B. (2019). Tips and tricks to improve survey response rate. SurveyMonkey. Retrieved from https://www.surveymonkey.com/curiosity/improve-survey- response-rate/
Rahman, M. S., & Adnan, T. M. (2020). Risk management and risk management performance measurement in the construction projects of Finland. Journal of Project Management, 5, 167–178. https://doi.org/10.5267/j.jpm.2020.5.001
Safaeian, M., Fathollahi-fard, A. M., Kabirifar, K., & Yazdani, M. (2022). Selecting Appropriate Risk Response Strategies Considering Utility Function and Budget Constraints?: A Case Study of a Construction Company in Iran.
Salatoom, N., & Taneerananon, P. (2015). A study of a flyover-bridge - improved intersection. Engineering Journal, 19(1), 1–12.
Sharma, S., & Gupta, A. K. (2019). Risk Identification and Management in Construction Projects: Literature Review. International Journal of Humanities, Arts and Social Sciences, 5(6), 224–231. https://doi.org/10.20469/ijhss.5.20002-6
Siraj, N. B., & Fayek, A. R. (2019). Risk Identification and Common Risks in Construction: Literature Review and Content Analysis. Journal of Construction Engineering and Management, 145(9), 03119004. https://doi.org/10.1061/(asce)co.1943-7862.0001685
Tabish, S. Z. S., & Jha, K. N. (2012). Success Traits for a Construction Project. Journal of Construction Engineering and Management, 138(10), 1131–1138. https://doi.org/10.1061/(asce)co.1943-7862.0000538
Takim, R., & Akintoye, A. (2002). Performance Indicators for Successful Construction Project Performance. 18th Annual ARCOM Conference., 2(September), 545–555.
Zantanidis, S., Tsiotras, G. (1998). Quality Management: A New Challenge for the Greek Construction Industry. Total Qual. Manage., 9(7): 619-653.
In-Text Citation: (Zain et al., 2022)
To Cite this Article: Zain, F. M. Y., Mohamed, A. A., Saidin, M. T., & Zainuddin, M. F. (2022). Identification Type of Risk with Evidence to Kelantan’s Flyover Projects. International Journal of Academic Research in Business and Social Sciences, 12(8), 1485– 1490.